Street & Utility Update

roadwork

June 28, 2023

To: Residents within the 2023 Street & Utility Project

Dear Residents,

Here is an update on the Street and Utility work. All timelines listed below are subject to change due to weather conditions or equipment breakdowns. 

Woodland Road & Highwood Drive

All work on these streets is completed.

Sommerset Avenue & Wirth Street

DC Burbach is scheduled to begin the concrete work on July 5th. The concrete work will be followed by the fine grading, which will be done by Payne & Dolan.

Garfield Street

Denny Rahn Excavating will finish the road work this week. The road work will be followed by the concrete work. DC Burbach will be performing the concrete work. They are scheduled to be on site within the next two weeks.

Alley between Franklin Avenue & Evergreen Boulevard

Denny Rahn Excavating is will begin road work this week. This will consist of removing 12 inches of existing asphalt, base and spreading 8 inches of new base course.

All streets continue to be closed to thru traffic. Due to the construction, roadway access and driveway access may be limited during working hours but will be restored at the end of the day.

We ask for your patience during the construction. The entire project will be completed by August 25, 2023. If you have any questions, concerns, or special requests, please let me know. I can be reached at City Hall at (262) 375-7610 or email me at durbanek@ci.cedarburg.wi.us.

CITY OF CEDARBURG

Dylan Urbanek, Assistant City Engineer