Street & Utility Update

roadwork

June 20, 2023

To: Residents within the 2023 Street & Utility Project

Dear Residents,

Here is an update on the Street and Utility work. All timelines listed below are subject to change due to weather conditions or equipment breakdowns. 

Woodland Road & Highwood Drive

Payne & Dolan has finished the fine grading. Dorner will be on site to adjust manholes the next couple of days. Payne & Dolan will return on Thursday and Friday to perform the paving.

Sommerset Avenue & Wirth Street

Denny Rahn Excavating will finish the road work sometime this week. The road work will be followed by the concrete work. The concrete work will be done by DC Burbach. They are scheduled to begin the week of July 3.

Garfield Street

Denny Rahn Excavating will begin the road work later this week. The road work consists of removing 14 inches of existing asphalt, base and spreading 9 inches of new base course. The road work will be followed by the concrete work.

Alley between Franklin Avenue & Evergreen Boulevard

Denny Rahn Excavating is scheduled to begin road work sometime in mid-July. This will consist of removing 12 inches of existing asphalt, base and spreading 8 inches of new base course.

All streets continue to be closed to thru traffic. Due to the construction, roadway access and driveway access may be limited during working hours but will be restored at the end of the day.

We ask for your patience during the construction. The entire project will be completed by August 25, 2023. If you have any questions, concerns, or special requests, please let me know. I can be reached at City Hall at (262) 375-7610 or email me at durbanek@ci.cedarburg.wi.us.

CITY OF CEDARBURG

Dylan Urbanek

Assistant City Engineer