Construction Update

street closed

October 6, 2021

2021 Asphalt Pavement Repair Project on Washington Avenue (Center Street to Hamilton Road)

CONSTRUCTION SCHEDULE UPDATE

Thursday, October 7th – Installation of 1” Asphalt Leveling Layer

Friday, October 8th – Installation of Asphalt Interlayer Grid

Saturday, October 9th – Installation of 2” Asphalt Surface Layer

Week of October 11th – Pavement Markings

Washington Avenue within the construction zone will need to be completely closed after the asphalt interlayer grid is installed until it is covered with the asphalt surface layer.  Washington Avenue will then remain closed to thru traffic until the pavement markings have been placed.

All dates are subject to change due to weather conditions.

If you have any questions, please feel free to contact the City of Cedarburg Engineering Department at 262-375-7610.