2023 Street & Utility Resident Update

roadwork

April 21, 2023

To: Residents within the 2023 Street & Utility Project

Dear Residents,

Here is an update on the Street and Utility work. All timelines listed below are subject to change due to weather conditions or equipment breakdowns. 

Woodland Road & Highwood Drive

Dorner Inc. will be completing the utilities sometime in the next week. The utility work will be followed by the road work. Denny Rahn Excavating will begin the roadwork sometime in the first couple of weeks of May. The roadwork involves removing 14 inches of existing asphalt, base and spreading 9 inches of new base course.

Sommerset Avenue & Wirth Street

Dorner Inc. is scheduled to begin work on May 1st. They will begin working on watermain on Wirth Street.

Garfield Street

Dorner Inc. is scheduled to begin work on May 30th.

Alley between Franklin Avenue & Evergreen Boulevard

Denny Rahn Excavating is scheduled to begin roadwork sometime in mid to end of May. This will consist of removing 12 inches of existing asphalt, base and spreading 8 inches of new base course.

All streets continue to be closed to thru traffic. Due to the construction, roadway access and driveway access may be limited during working hours but will be restored at the end of the day.

We ask for your patience during the construction. The entire project will be completed by August 25, 2023. If you have any questions, concerns, or special requests, please let me know. I can be reached at City Hall at (262) 375-7610 or email me at durbanek@ci.cedarburg.wi.us.

CITY OF CEDARBURG

Dylan Urbanek, Assistant City Engineer